Construction Elements
|
Introduction The Katrine Water Project is a multifaceted project, comprising of a number of different individual construction activities throughout the Strathblane, Milngavie and Balmore area. The various elements making up this programme of work are described below, along with a record of construction progress
|
|
Water Treatment Works and Service Reservoir |
||
|
Start Date |
Finish Date |
Estimated Cost |
|
March 2004 |
December 2007 |
The latest cost estimate for the project is £120 million. This is part of Scottish Water's investment programme of £1.8bm for 2003-06. |
|
|
Construction of the main works at Milngavie
started on 22 March 2004. The scope of works will include:-
|
|
|
For easy reference we have split the works into three areas a, b and c as detailed below. Click on the links below for further information and photographs to date. Area A: Clearwater Tank, Raw Water Pumping Station and Access Road Area B: Water Treatment Works Area C: Service Reservoir, Pipelines and Network Reinforcement |
||
| New Milngavie Water Treatment Works - Contractors Code of Conduct | ||
| Mugdock Reservoir Drawdown | ||
| Area C - Bankell Service Reservoir goes into supply, 24 May 2006. - Improved Supply for Glasgow Water Users In the initial phase approximately 200,000 customers in the City Centre and West End will be supplied. | ||
| Craigmaddie Reservoir Drawdown | ||
|
Balmore to C5 Main |
||
|
Start Date |
Finish Date |
Estimated Cost |
| September 2002 | February 2004 | £5 Million |
![]()
Description of Works: This route consists of twin 900 mm diameter ductile iron pipes, linking the existing Water Treatment Works at Balmore to the existing 36" (900 mm) cast iron C5 Main at Bardowie Loch, adjacent to Craigmaddie Road. The route is approximately 2 km in length. This new main provides a treated water supply to some 140,000 customers in the East of Glasgow. This new supply is made possible by the introduction of the Strathblane Cross Connection which transfers a proportion of Loch Katrine Water to Balmore Water Treatment Works. The pipelines between Balmore Water Treatment Works and the existing C5 main have been completed. Re-instatement has been carried out over the summer season and progress has been assisted by the favourable weather. Final re-instatement is programmed for completion by Spring 2004. The connection into the C5 was started and completed over a 48 hour period on 19 and 20 August 2003. The intrusive operations to form the connection to the 36" diameter pipe was successfully carried out without any disruption to the 140,000 customers supplied by the C5 main. Pressure testing and disinfection of the new twin pipeline has been completed during September 2003. Photographs of Official Opening Scottish Water Press Release - New Water Supply for Glasgow's East End
|
||
| Katrine Water Project Balmore - C5 Main Contractors Code of Conduct | ||
|
Strathblane Cross Connection |
||
|
Start Date |
Finish Date |
Estimated Cost |
| October 2001 | July 2002 | £1.9 Million |
|
All construction work on the Strathblane Cross Connection has been completed
Schematic of Existing Loch Lomond/Loch Katrine Infrastructure
|
||
| Description of Works | Photographs | Commissioning Ceremony |
|
Pilot Plant |
||
|
Start Date |
Finish Date |
Estimated Cost |
| May 2001 | July 2002 | £1 Million |
|
The Pilot Plant superstructure has been cleared and the area previously occupied is presently being used by the Contractor carrying out security fencing operations. Final re-instatement of the area will be carried out during 2004 after the contractors operations have been completed.
|
||
| Description of Works | Photographs | Schematic |